Roofing job handoff: is an accepted job ready to schedule?
Between an accepted roofing estimate and the first day on the roof, several things must be true: the scope is confirmed, materials are available, the site is accessible, the weather window is workable and a crew has the hours. A short handoff gate keeps jobs from being scheduled before they are ready.
By ZeroDelay.ai · An educational framework, not a customer case study
A question to start with
Before a job goes on the calendar, has each readiness item been confirmed, and does the crew actually have the hours?
Step 1
Confirm the scope at handoff
The person who sold the job and the person scheduling it review the same accepted scope: roof areas, tear-off, decking allowance, disposal and any exclusions. Note who confirmed it and when, so the crew does not start from an older version.
Step 2
Check materials, access and weather
Record whether materials are ordered, confirmed or delivered; whether access, parking and any permits are arranged; and the planned weather check date. Each item is yes, no or pending. Weather decisions and safety stay with the qualified people on site.
Step 3
Match person-hours to the crew day
Estimate person-hours for each job including setup, travel and cleanup, then compare the total with the crew's available person-hours that day. If there is no spare time, adding another job means moving something, not squeezing it in.
Records to gather first
- Accepted estimate and the latest approved scope version.
- Material order confirmations and delivery dates.
- Access notes, permit status and any customer scheduling limits.
- Crew roster with available hours by day.
- Recent actual job durations for similar work, to sanity check estimates.
Copy or print this blank worksheet
Copy the table into your own document or use your browser's Print command, then fill it in there or on paper. There are no entry fields here, nothing is saved, and numbers you write do not transfer into the diagnostic.
| Job / reference | Scope confirmed | Materials ready | Access / permit ready | Weather check date | Est. person-hours | Crew assigned | Ready to schedule |
|---|---|---|---|---|---|---|---|
| Job 1 | ______ | ______ | ______ | ______ | ______ | ______ | ______ |
| Job 2 | ______ | ______ | ______ | ______ | ______ | ______ | ______ |
| Job 3 | ______ | ______ | ______ | ______ | ______ | ______ | ______ |
| Job 4 | ______ | ______ | ______ | ______ | ______ | ______ | ______ |
| Travel and setup | ______ | ______ | ______ | ______ | ______ | ______ | ______ |
| Total person-hours | ______ | ______ | ______ | ______ | ______ | ______ | ______ |
Fictional worked example
All figures are made-up assumptions to show the arithmetic. They are not industry benchmarks, customer data, achieved outcomes or a forecast for your business.
Assumptions
- Fictional single crew of 2 people, each available 7 hours on the planned day.
- Two handed-off jobs are estimated at 6 and 5 person-hours, plus 3 person-hours of travel and setup between them.
- Both jobs have scope, materials and access confirmed; a third accepted job is waiting on materials.
Simple math
- Crew capacity: 2 people × 7 hours = 14 person-hours.
- Planned work: 6 + 5 + 3 = 14 person-hours.
- Spare capacity: 14 − 14 = 0 person-hours. The third job fails the handoff gate on materials and also has no crew time that day.
What this suggests checking: The day is full on paper with no slack. Adding the third job would require moving another job or another crew day, and it is not ready anyway. The gate keeps the calendar honest rather than optimistic.
Review readiness: ready versus blocked, with an owner for each gap
The 14 person-hour example above shows a full day. The next review is whether each accepted job is actually ready. Accepted means the customer agreed; ready means every gate item has evidence. The fictional ready rows below assume all required scope, materials, access, permit and qualified weather checks are confirmed; the table lists example evidence, not an exhaustive clearance checklist. A single pending dependency holds the start date.
Separate fictional scenario for teaching only. It does not change the worked example above and is not a benchmark, customer result or forecast.
| Job | Status | Pending item | Required evidence | Owner | Est. person-hours |
|---|---|---|---|---|---|
| Job A | Ready | None | Signed scope version, delivery confirmation, access note | Scheduler | 6 |
| Job B | Ready | None | Signed scope version, delivery confirmation, access note | Scheduler | 5 |
| Job C | Blocked | Materials | Supplier delivery confirmation with date | Purchasing lead | Not scheduled |
Check the arithmetic
- Ready jobs: 6 + 5 = 11 person-hours, plus 3 person-hours of travel and setup = 14, matching the crew's 14 person-hours.
- Person-hours are not clock-hours: 14 person-hours equals 7 hours with both people available throughout. It does not guarantee a job takes 7 elapsed hours.
- Job C stays off the calendar until its one pending item has evidence, even though it is accepted.
Investigate when
- Any job marked ready without the named evidence attached or referenced.
- Blocked jobs with no owner or no expected evidence date.
- Days where ready person-hours exceed the crew's available person-hours.
Next actions
- The named owner confirms the pending item and records the evidence; only then does the scheduler pick a date.
- Tell the customer the job is accepted and waiting on a named item, rather than giving a start date.
If the same gate item blocks jobs repeatedly, find recurring scheduling bottlenecks.
What this cannot tell you
- Estimated person-hours are planning figures; actual duration varies.
- This worksheet is a business scheduling aid, not safety, weather or building-code guidance.
- Fictional figures; not roofing productivity benchmarks.
- Estimate conversion and won-job margin are covered separately in the roofing follow-up and margin guide.
Choose a next step from your worksheet
Use the handoff gaps to separate work that is ready to schedule from estimates still awaiting a customer decision. Separate roofing estimate follow-up from job margin.
For a separate, no-signup calculation, open the free Profit Leak Check. Choose roofing to compare estimate follow-up counts and recorded job revenue/direct costs; it does not schedule crews or validate a handoff. Calculations stay in your browser.
If this worksheet raises a wider business question, the diagnostic below uses the answers you provide about your business; it does not import this worksheet or calculate its results. View the fictional sample 90-Day Plan to see an illustrative complete paid report, not your free results or a promised outcome. Available market research varies.