Electrical estimate scope changes: allowances and approvals
Scope changes are easier to handle when the original estimate says plainly what is included, what is an allowance and what is excluded. Recording each change as a new version with explicit customer approval and its incremental direct cost shows what the change did to job contribution. This is a business record-keeping workflow only; it is not electrical, code or legal advice.
By ZeroDelay.ai · An educational framework, not a customer case study
A question to start with
When the work changes, can you show what the original estimate allowed, what the customer approved, and what the change cost before overhead?
Step 1
Separate allowance from exclusion
On the original estimate, list included work, any allowance (a stated quantity or amount for uncertain items) and work that is excluded. When something new comes up, check which list it belongs to before discussing price.
Step 2
Version the scope and get explicit approval
Write the change as a numbered version: what is added or removed, the price change and the date. Record the customer's explicit approval in the way you normally document agreements before the changed work starts. Do not treat a verbal comment as approval if your own records cannot show it.
Step 3
Cost the change incrementally
Record the additional direct labor and materials the change used. Combine with the original job to see total revenue, direct cost and contribution before overhead and tax. Contribution is not net profit.
Records to gather first
- Original estimate with included work, allowances and exclusions.
- Each scope version with date, description and price change.
- Record of customer approval for each version.
- Actual direct labor hours and material costs for the original work and each change.
- Collected amounts for the original job and each approved change.
Copy or print this blank worksheet
Copy the table into your own document or use your browser's Print command, then fill it in there or on paper. There are no entry fields here, nothing is saved, and numbers you write do not transfer into the diagnostic.
| Version | Description of change | Allowance or excluded | Approval recorded (date) | Price change $ | Direct labor $ | Materials $ | Contribution $ |
|---|---|---|---|---|---|---|---|
| Original estimate | ______ | ______ | ______ | ______ | ______ | ______ | ______ |
| Change 1 | ______ | ______ | ______ | ______ | ______ | ______ | ______ |
| Change 2 | ______ | ______ | ______ | ______ | ______ | ______ | ______ |
| Change 3 | ______ | ______ | ______ | ______ | ______ | ______ | ______ |
| Combined job | ______ | ______ | ______ | ______ | ______ | ______ | ______ |
Fictional worked example
All figures are made-up assumptions to show the arithmetic. They are not industry benchmarks, customer data, achieved outcomes or a forecast for your business.
Assumptions
- Fictional job: original estimate collected $1,200 with $760 of direct cost.
- One excluded item was requested and approved as version 2, collected at $300.
- The change used $140 of direct labor and $60 of materials.
Simple math
- Original contribution: $1,200 − $760 = $440.
- Change contribution: $300 − ($140 + $60) = $100.
- Combined revenue: $1,200 + $300 = $1,500. Combined direct cost: $760 + $140 + $60 = $960.
- Combined contribution: $1,500 − $960 = $540, before overhead and tax. This is not net profit.
What this suggests checking: The approved, versioned change added $100 of contribution and left a clear record. If the same work had been done without approval, the $200 of direct cost would have reduced the original $440 to $240 with no matching revenue.
Review approved versus unapproved change work side by side
Using the same fictional job, compare an approved, collected change with a scenario where the same extra work was done but no extra amount was collected. The comparison assumes the original $1,200 is collected either way. Lack of approval does not establish the amount legally owed or recoverable; this is a cost-and-collection illustration, not a legal conclusion.
Separate fictional scenario for teaching only. It does not change the worked example above and is not a benchmark, customer result or forecast.
| Line | Collected revenue $ | Direct cost $ | Contribution $ before overhead and tax |
|---|---|---|---|
| Original estimate | 1,200 | 760 | 440 |
| Approved change (labor 140, materials 60) | 300 | 200 | 100 |
| Total with approved change | 1,500 | 960 | 540 |
| Same extra work, no extra collection assumed | 1,200 | 960 | 240 |
Check the arithmetic
- Approved: $440 + $100 = $540 combined contribution, before overhead and tax.
- Unapproved: $1,200 − ($760 + $140 + $60) = $240, assuming the original amount is still collected in full.
- Difference in this fictional comparison: $540 − $240 = $300, the uncollected change price. This is contribution, not net profit.
Investigate when
- Any direct cost recorded against a job with no matching approved version.
- Change requests for items the original estimate listed as allowances, to check whether the allowance was used up first.
- Approvals dated after the changed work started.
Next actions
- Before changed work starts, record the version number, price change and approval in your normal agreement record.
- For questions about contracts or collecting disputed amounts, consult a qualified professional; this review makes no legal assessment.
When pricing a change version, separate gross margin from markup.
What this cannot tell you
- Business workflow only; not electrical, code, safety or legal advice. Consult qualified professionals for those questions.
- Contribution before overhead and tax is not net profit.
- Fictional figures; not typical prices or margins.
Choose a next step from your worksheet
Use the approved scope record to compare the original cost estimate with what the job actually used, without treating unapproved work as revenue. Review estimate-versus-actual job costs.
If this worksheet raises a wider business question, the diagnostic below uses the answers you provide about your business; it does not import this worksheet or calculate its results. View the fictional sample 90-Day Plan to see an illustrative complete paid report, not your free results or a promised outcome. Available market research varies.